October 2020 update

October 01, 2020

Wilton Park this Summer

We are conducting demolition works which focus on the existing vacant MoD buildings within phase 1 of the site. Having started in July, we expect the work to be completed by the end of November.

This Autumn

Our work on site is in preparation for a Council decision on our ‘Reserved Matters Planning Application’. Submitted in June 2020, this application seeks permission to deliver the first two phases of development at Wilton Park which, if approved, will be 147 new homes.

This ‘Reserved Matters’ application builds on the Outline Planning consent granted to Inland Homes by South Bucks Council in September 2019. Only with Reserved Matters approval can we complete the A355 Relief Road, and we are continuing to work closely with the Local Authority to achieve this approval.

We do hope this update is helpful, and we look forward to the Council determining our application in the near future so that we can deliver on our exciting vision for a new Wilton Park.